Dear Esteemed Le Rêve Community,
We are pleased to bring you our latest construction update as Le Rêve enters its most recent phase. With the structural frame complete and the tower at its full height, our focus has now turned to interior finishing, services installation and the fine details that will define the quality of every residence.
The pace on site remains strong and our team continues to work diligently across multiple floors simultaneously to maintain our delivery schedule.
Site Video
The following footage was captured on site in late April 2026, offering a closer look at the progress across the tower.
Looking Ahead
- Tiling and Floor Finishes: Tile installation will continue on completed and screeded floors, bringing the residences closer to their finished state.
- Painting and Wall Finishes: First coat painting will begin on plastered and prepared wall surfaces across lower floors.
- Lift Installation: Works on the lift shaft and installation of lift equipment will progress during this phase.
- External Facade Works: Ongoing external cladding and facade finishing to complete the tower's exterior presentation.
As always, your patience and trust in our team mean everything to us. Le Rêve is coming together as a residence worthy of the name, and we look forward to sharing the next milestone update with you very soon.
The August Crossing Team